Introduction on the MRT Line:

The total length of the MRT Green Line is about 16.7 kilometers, which starts from around Songzhu Road 2nd Bridge of Beitun District in the east and runs southwards into HSR Taichung Station and composes 18 stations. Construction of interior station renovation, the testing of electromechanical sub-systems, and the integrated testing of all electromechanical parts are completed. MOTC completed its final inspection on Oct. 25, 2020 and the permit for operation was applied for on Nov. 2, 2020. Its operation was permitted by MOTC on Nov. 6, 2020 and trial operation was practiced from Mar. 25 to Apr. 23, 2021. It was officially put into service on Apr. 25.